Case
Histories - Fox Wins: Sewer Sinks to New Depths
The City of Bakersfield,
CA, wanted to open the rugged foothills northeast of the city for residential
development. The area had been annexed into the city in the 1970s but growth was
slow. Municipal officials turned to Porter-Robertson Engineers for recommendations
on providing sewer service to the area. Three options were considered by the Bakersfield
consulting firm: Develop a community leach field system, construct a package treatment
plant, or run a new sewer line to the proposed development from an existing treatment
facility. The up-front cost of running the line was more than the other options.
However, officials determined that in the long run it was the more cost- efficient
option. The projected fees for the community leach system and the package treatment
facility would have been far in excess of the projected $700 per dwelling fee
to connect to a new sewer line.
A number of thermoplastic pipe materials
were considered along with vitrified clay. Bids ranged from $4.7 to $7.2 million.
The project was won by Speiss Construction of Santa Maria, CA. The material of
choice for the large diameter requirements of the line was Vylon PVC pipe.
Over 20, 000 feet of 21 to 30 inch pipe was installed by the contractor at some
unexpected depths.
Habitat Conservation Plan
As
the consulting firm worked on the planned route of the new line, Jim Movias, principal
planner with the Bakersfield Development Services Department, was putting the
finishing touches on a Habitat Conservation Plan. The goal of the plan is to protect
the area's natural habitat and meet the requirements of state and federal endangered
species acts. Consistent with the plan, a biostudy was conducted to identify wildlife
within the proposed corridor of he pipe. The study revealed that within pipe's
path were a number of dens belonging to the endangered San Joaquin Kit Fox.
The Kit Fox dens were located in a fairly deep ravine directly along the
pipe route. To avoid disturbing the dens, the alignment of the pipe was moved
300 feet p the hill. The move increased the burial depth of the pipe to approximately
37 feet, necessitating stacked trench boxes. DeWayne Starnes, P.E. with
the City's public Works Department observed, "We ere comfortable with placing
the product at the extreme depths necessitated by these conditions."
In addition to the challenges of working at this depth, construction crews had
to adapt to a variety of soil conditions including cobble boulders and blue-clay.
Silty-and runs through the foothills making trench walls unpredictable.
Under the supervision of the Bakersfield Construction Supervisor, Gerry Claassen,
a contract inspector from Porter Robertson Engineers monitored the quality of
construction. Soil samples were sent to an independent lab for testing. Bedding
consisted of screened native material. Ninety percent compaction was achieved
in the pipe zone; 85 percent was achieved one foot above the pipe to the surface.
The pipe passed a low-pressure air test the first time. A go-no-go steel mandrel
was pulled through the line. Results were within the 5 percent deflection specification.
According to the City of Bakersfield, the pipe, which has been in service
for over one year, is performing to standard without leakage. The performance
of the pipe is no surprise to Fred Porter of Porter Robertson Engineers, who frequently
visited the site during construction. "The pipe has a unique four-finned gasket
that really locks those joints together." Since completion of the line,
a new magnet school has been constructed in the area and residential development
is moving at a rapid pace. |