PRIME CONDUIT VYLONÒ PVC LARGE DIAMETER

CLOSED PROFILE GRAVITY SEWER PIPE

STANDARD SPECIFICATIONS

 

I.          GENERAL

 

A.         SCOPE

The work in this section includes furnishing all labor, equipment, and materials required to supply, install, and test (PVC) closed profile wall pipe, including accessories, as shown on the drawings and/or specified herein.

 

            B.        QUALITY ASSURANCE

1.       The contractor shall submit to the Engineer written evidence that the pipe furnished under this specification is in conformance with the material and mechanical requirements specified herein.  Certified copies of independent laboratory test results from the pipe supplier may be considered evidence of compliance provided such tests are performed in accordance with the appropriate ASTM testing standards by experienced, competent personnel.

2.       Each PVC closed profile wall pipe length and fitting shall be clearly marked with the following:

            a.   Manufacturer’s Name

            b.   Nominal Pipe Size

            c.   Cell Classification

            d.   ASTM F 1803 Designation

            e.   Pipe Stiffness - 46 PSI

3.   All pipe shall be factory air tested with gasket in place and marked accordingly.

 

C.        SHOP DRAWINGS AND ENGINEERING DATA

1.       Complete shop drawings and engineering data on all piping and accessories shall be submitted to the Engineer in accordance with the submittal requirements of the project specifications.

 

            D.        HANDLING/STORAGE

1.       The pipe shall be handled carefully with nylon slings.  The pipe can be unloaded/transported with construction equipment rigged with an “extra long fork” attachment.

2.       All pipe and accessories shall be stored on flat, level ground with no rocks or other objects under the pipe.

3.       The maximum recommended stacking height for PVC closed profile wall pipe is given below:

                                                           

                                                            Pipe Size                                 Number of Rows

                                                              21 inch                                                6

                                                              24 inch                                                5

                                                              27 inch                                                5

                                                              30 inch                                                4

                                                              36 inch                                                3

                                                              48 inch                                                2

                                                              54 inch                                                1

 

II.         PVC PIPE MATERIALS

 

            A.         GENERAL

1.       Apart from structural voids and hollows associated with profile wall designs, the pipe and fittings shall be homogenous throughout and free from visible cracks, holes, foreign inclusions and other injurious defects.  The pipe shall be as uniform as commercially practical in color, opacity, density and other physical properties.

2.       Unless otherwise shown on the drawings or directed by the Engineer or manufacturer, the maximum depth of cover, measured from the pipe crown to the ground surface, permitted for all 21” to 54” sizes of VylonÒ Pipe PS-46 will be 50 ft. with standard bedding. (See Bedding Recommendation sheet.)  The allowable depths are based on the assumption that the ground water level or phreatic surface is at surface grade elevation. For less severe conditions deeper installations are acceptable. Consult pipe manufacturer for recommendations.

 

B.        PVC LARGE DIAMETER CLOSED PROFILE PIPE

1.       PVC profile wall pipe and fittings shall be manufactured in accordance with the requirements of ASTM F 1803 latest edition.

2.       PVC profile wall pipe shall be made from a compound meeting the requirements of cell classification 12364A as defined by ASTM D 1784. (See Specification and Properties Sheet for VylonÒ Pipe & Fittings.)

 

            C.        JOINTS

1.       PVC profile wall pipe joints shall be the bell and spigot type.

2.       Gaskets shall meet the requirements of ASTM F 477 and be molded into a circular form or extruded to the proper section, then spliced into circular form, and shall be made of a properly cured high grade elastomeric compound.

3.       Gaskets shall be factory installed and chemically bonded to the bell end of the pipe.  Field installed gaskets and field cut beveled lengths of pipe shall be done in accordance with the manufacturer’s instructions and recommended equipment and materials.

4.       All pipe gaskets and spigots will be thoroughly cleaned and lubricated before assembly.

 

III.        INSTALLATION REQUIREMENTS

 

            A.         GENERAL

                        Installation shall be in accordance with the recommendations contained herein and in the pipe manufacturer’s installation guide.  All applicable safety regulations shall be followed:

 

            B.        FILL MATERIALS

1.       Pipe Bedding and Backfill Materials:

a.   Class I. The following materials will be considered Class I in this specification.

(1)  ASTM D 448 - Stone Sizes No. 5, 56, 57, 6, 67, and 68.

(2)  Clean, well graded crushed rock with a maximum particle size of 1” and with not more than five percent (5%) passing the #8 Sieve.

(3)  #10 CHAT (rock crusher tailings) or regional equal.

b.   Class II.  Coarse grain soils with little or no fines such as GW, GP, SW and SP containing less than twelve percent (12%) fines. Maximum particle size - 1”.

c.   Class III. Coarse grain soils with fines. GM, GC, SM and SC containing no more than twenty-five percent (25%) fines. Maximum particle size to be less than 1”.

d.   Where cement stabilized sand is used, it shall be eight percent (8%) minimum by weight Port-land Cement. The sand aggregate shall be clean with less than ten percent (10%) fines and meet Standards for concrete sand. Cement sand shall have a minimum unconfined compressive strength of 300 psi at seven (7) days. All cement and sand shall be placed and compacted within two and one half (2 ½) hours after application of water. After placement, it shall be protected against drying for seven (7) days.

 

            C.        TRENCH PREPARATION

1.       Trench Excavation

a.   TRENCHING: Trenches shall be open cut to proper depth and alignment for the installation of pipe and appurtenances as shown on the Plans. The overall trench width within the pipe zone shall be shown on the Plans for the appropriate type of pipe and shall be as follows:

                             

                                                                                 Minimum

                              Pipe Diameter                         Trench Width

                                   21” - 54”                               Pipe O.D. + 18”

     

There is no restriction on the maximum trench width.       

Shoring of trenches shall follow the requirements set forth in the soils report and State and Federal Safety requirements. If trench sloping is substituted for shoring, the slope shall be in accordance with all applicable safety regulations. Trench walls below the elevation of the pipe crown should be maintained as vertical as possible.

      Where excavation causes caving, excavation within the pipe zone to be wider than specified, the Contractor shall remove all loose and sloughed in material from the trench and replace with compacted granular material.

      Where the bottom of the trench at sub grade is found to be spongy and soft or includes organic material, the Contractor shall excavate and remove such undesirable materials to the width of the trench and depth of at lease six (6) inches or as required so as to provide a firm foundation for the pipe. The over-excavation shall be replaced with granular material and compacted to a minimum of eighty-five (85%) Standard Proctor per ASTM D 698.

b.   DEWATERING: The Contractor shall provide and maintain at all times during construction ample means and devices with which to promptly remove and properly dispose of all water, from any source whatsoever, entering the trench or structure excavation or other parts of the work.

      Pipe trenches or structure excavation shall be kept free from water during excavation, construction, pipe laying and joining. The method of dewatering shall maintain a phreatic water surface below the bedding material.

c.   ROCK EXCAVATION: Rock is defined as sound and solid masses, layers, or ledges.

      Whenever trenching is required through rock, the rock shall be removed to the width of the trench and to a minimum depth of four (4) inches below the pipe barrel. The over-excavation shall be replaced with granular material.

d.   TRENCH SUPPORT: If trench support is used, the Contractor shall follow the recommendations in the pipe manufacturer’s installation guide and comply with all applicable safety regulations.

      Shoring, sheeting or trench shields shall be utilized in such a manner as to minimize disturbance of the bedding material beneath the pipe crown. Whenever possible, trench support should not extend below the pipe crown. If trench support is necessary below the crown, it should either be left in place or consist of steel sheets ¾” thick or less which can be extracted with minimal disturbance.

      Dragging of a trench shield at pipe grade should only be done when it is demonstrated that such practices will not disturb the bedding, such as with the use of a compaction shield (or cut out section) at the trailing edge of the shield. If a trench shield inadvertently slips below the pipe crown it should be raised vertically and granular embedment material should be placed and compacted in the void created by the shield.

 

IV.       PIPE LAYING

A.   Before sewer pipe is placed in position in the trench, the bottom and sides of the trench shall be carefully prepared, the required bedding placed, and bracing and sheeting installed where required. The trench shall be excavated to the dimensions shown on the drawings. Each pipe shall be accurately placed to the line and grade called for on the drawings. Grade shall be controlled by a laser beam or batter boards and a Mason’s line.

B.   All pipe and fittings shall be inspected before it is placed in the trench.

C.   Pipe laying shall proceed upgrade, starting at the lower end of the grade and with the bells uphill.

D.   Trench bottoms found to be unsuitable for foundations after pipe laying operations have started shall be corrected and brought to grade with approved compacted materials.

E.   Pipe trenches shall be kept free from water during pipe laying, joining or before sufficient backfill has been placed to prevent flotation of the pipe. The Contractor may use sump pumps, well points, or any other devices to remove water from the trench bottom. Small puddles that are no closer than 4” from the bottom of the pipe are acceptable. The Contractor shall provide ample means and devices to promptly remove and dispose of all water from any source entering the trench.

F.   No connection shall be made where joint surfaces and joint materials have been soiled by earth or embedment in handling until such surfaces are thoroughly cleaned.

G.   As the work progresses, the interior of all pipes shall be kept clean. After each line of pipe has been laid, it shall be carefully inspected and all earth, trash, rags, and other foreign matter removed from the interior.

H.   Backfilling of trenches shall be started immediately after the pipe is placed in the trench.

I.    Backfill material placed under the haunches shall be shovel sliced or compacted depending on class of embedment.

 

J.         PIPE BEDDING

1.   General: Where the depth of cover is twenty-five (25) feet or less, pipe bedding for 21” - 54” pipe shall be defined as that portion of the pipe zone which extends from 4” below the bottom of the pipe to a point 6” above the top of the pipe. Where depth of cover exceeds twenty-five (25) ft., the pipe zone shall extend to 12” above the top of the pipe.

2.   Bedding Material: The pipe bedding shall be Class I, II, or III material as defined on the previous page and shown on the Bedding Recommendation Sheet.  Prior to laying the pipe the foundation material shall be trimmed to grade, such that each pipe section is fully supported along the entire length of the pipe barrel.

 

            K.        TRENCH BACKFILLING

1.  General: All trenches shall be backfilled immediately after the pipe has been laid and inspected. Backfilling shall include the refilling and compaction, where required of the fills in the trenches or excavation to the existing ground surface or to the existing road sub grade.

     Following the laying of the pipe, the pipe shall be centered in the trench, adjusted to line and grade, and the initial bedding material shall be carefully placed on both sides of the pipeline. The bedding material shall be sliced under the haunches of the pipe to fill all voids.  The slicing shall be per-formed when the bedding material is no higher than 12” above the bottom of the pipe.

2.  Bedding: Bedding material shall be placed within the pipe zone 4” below the pipe to 6” above the pipe crown as shown in the Bedding Recommendation Sheet.

     Bedding material shall be Class I, Class II or Class III as defined in Section III-B “Fill Materials”.

3.  Backfilling Within the Pipe Zone: The pipe zone shall be backfilled with bedding material and where required compacted by mechanical means as shown in the Bedding Recommendation Sheet.  Where the cover depth is less than or equal to twenty-five (25) ft., Class I backfill does not require compaction. Class I material must be shovel sliced under the haunches and voids eliminated.

4.  Backfill Above the Pipe Zone: The remaining portion of the trench from the pipe zone to the existing ground level or road sub grade shall be backfilled with material excavated from the trench. The back-fill material shall be free of rubbish, frozen material, broken pavement, other debris, and stones greater than 4” in diameter, organic material, or other material considered deleterious for a distance of at least two (2) ft. above the pipe crown.

 

            L.         CONSOLIDATION FOR CLASS II, III MATERIALS

1.   General: Pipe zone backfill for Class II and III materials shall be compacted by mechanical tampers, vibrators, or other mechanical means.

      Backfill shall be compacted by equipment suitable for the type of soil encountered and capable of producing the degree of compaction specified. Backfill materials shall be moisture conditioned to produce the required degree of compaction.

2.   Compaction Within the Pipe Zone: Where required backfill material within the pipe zone shall be compacted to eighty-five(85%) of the Standard Proctor Density as defined by ASTM D 698 “Standard Method of Test for Moisture - Density Relations of Soils using 5.5 lb. (2.5 Kg) Rammer and 12” (304.8mm) Deep” or to a sixty-five percent (65%) of relative maximum density, as defined by ASTM D 2049, “Standard Method of Test for Relative Density of Cohesion less Soils.”

      When backfilling within the pipe zone, special care shall be exercised not to cause settlement or lateral movement. To safeguard against movement of pipelines or structures, the Contractor shall place the backfill in suitable small layers and shall thoroughly compact each layer with hand-operated, power-driven vibrating compactors to obtain the specified density.

3.   Compaction Above the Pipe Zone: Compaction above the pipe zone shall be done in accordance with Standard “Owner” Specifications. Backfill to be compacted by heavy compaction equipment shall be placed in horizontal layers, prior to compaction; however, heavy compaction equipment shall not be used closer than 2 ft. to the top of the pipe.

 

            M.        CONCRETE CAP OR CEMENT STABILIZED SAND EMBEDMENT

Where pipe is located in a flood plain or otherwise susceptible to flotation it shall be anchored against flotation. The following are examples of acceptable methods of anchoring. Other methods may be used subject to the Engineer’s approval.

1.   Concrete Cap: The concrete cap will be poured on top of pipe after it has been placed and backfilled to within 4” of its crown. The cap will be a continuous strip with a minimum thickness of 12” and a minimum width of 4.0’ centered on the pipe. Six #4 bars shall be placed in the cap parallel to the axis of the pipe to provide temperature reinforcement.

2.   Cement Stabilized Sand Embedment: The pipe shall be embedded in cement stabilized sand from 6” below to 12” above the pipe. Cement sand shall be compacted to a minimum of ninety percent (90%) Standard Proctor Density within plus or minus two percent (2%) of optimum moisture content. Compaction shall be accomplished in 6” - 8” thick lifts.

3.   Berming: A minimum of 3 ½ feet of compacted fill shall be placed over the pipe.

 

V.        INSTALLATION OF SERVICE

A.   Lateral connections to PVC profile wall pipe may be made using Inserta-tee as manufactured by the Fowler Manufacturing Company, or the Predco Fast Fit tap system.

B.   All saddle or tapping tees will be installed per manufacturer’s recommendation. If exposed channels in the PVC profile with 3M industrial sealant No. 602 need to be filled.

 

VI.       CONNECTIONS

A.   Connections to existing lines shall be made by coupling a piece of PVC profile wall pipe to the existing line. The coupling shall be a JCM/Dresser solid sleeve which provides rigid support. Flexible rubber couplings with stainless steel clamps, such as Fernco or equivalent, may also be used.  The coupling is to be encased in concrete or cement stabilized sand.

B.   Connections to existing manholes or inlets, where no plugged stubs exist, shall be made by cutting a hole in the wall of the existing structure, inserting a length of PVC profile pipe into the hole, filing around the pipe with non-shrink grout, and troweling the inside and outside surfaces of the joint to a neat finish.  A manhole adapter or waterstop shall be placed on the pipe prior to placement in hole.  The bottom of the manhole shall be shaped to fit the invert of the sewer pipe.

C.   New manhole connections to precast concrete bases can be made with elastomeric gasket seals such as ALOK or Press Seal PSX.  Connections to poured in-place manholes shall use manhole adapters or waterstops.

 

VII.      PIPE TUNNELS AND CASING

A.   The pipe should not rest on the bell as it is pushed into the casing.  Skids should be used to raise and support pipe lengths in the casing.

B.   The annular space between PVC profile wall pipe and the casing pipe shall be filled with concrete grout or approved local embedment material. The Contractor’s procedure for placing the grout shall be approved by the Engineer.  After installation of pipe in casing, the casing shall be kept dewatered until grouting is completed.  Grout shall be placed by gravity flow following recommendations supplied by the pipe manufacturer.

 

VIII.     INSPECTION AND TESTING

A.   After completion of any section of sewer, the grades, joints, and alignment shall be true to line and grade.  There shall be no visual leakage and the sewer shall be completely free from any cracks and from protruding joint materials, deposits of sand, mortar or other materials on the inside, to the satisfaction of the Engineer.

B.   The Contractor shall conduct an infiltration or air test for leakage as determined by the Engineer.  Testing shall be conducted in accordance with all applicable safety standards.

C.   Infiltration Test: Infiltration shall not exceed twenty-five (25) gallons per twenty-four (24) hours per inch of diameter per mile of sewer.  Contractor shall furnish all supplies, materials, labor, services, etc., needed to make infiltration or exfiltration tests including water. No separate payment will be made for equipment, supplies, material, water, or services.

      Any leakage, including active seepage, shall be corrected where such leakage exists until the pipelines meet the requirements of the allowable leakage specifications.

      Infiltration tests shall be made when groundwater level is 18” or more above the top of the outside of the pipe.

D.   Air Test: Each section of sewer between two or more manholes shall be tested in accordance with ASTM F 1417, “Recommended Practice for Low Pressure Air Testing of Installed Sewer Pipe.”

      If any test fails to meet the established requirements the cause shall be determined and corrected if necessary.

E.   At the Engineer’s request, a deflection test shall be performed by the Contractor. The deflection can be measured mechanically by a mandrel or manually using an extension ruler. The final deflection test shall not be made on a section of sewer until all the backfill on that section has been in place for thirty (30) days.

      The minimum acceptable diameter shall be as follows:

 

Pipe Size

Minimum Acceptable Diameter (in.)

(in)

5% Test

7 ½% Test

21

19.11

18.61

24

21.65

21.08

27

24.41

23.77

30

27.18

26.46

36

32.71

31.85

42

38.23

37.22

48

43.61

42.47

54

48.98

47.69

 

All excess deflections shall be corrected.  The Contractor shall correct the deficiency and retest the pipe.

 

IX.       CLEANUP

After completing each section of the sewer line, the Contractor shall remove all debris, construction materials, and equipment from the site of the work, grade and smooth over the surface on both sides of the line and leave the entire right of way in a clean, neat and serviceable condition.

 

 

Disclaimer

 

This document contains accurate and reliable information to the best of our knowledge.  If this document is used to perform a design, it is required that the user have a thorough understanding of the subject, it’s applicability and it’s limitations.  This document should not be used in place of a professional engineer.  The user of this information assumes all risk associated with its use.



 

PRIME CONDUIT VYLONÒ ASTM F-1803

SPECIFICATIONS AND PROPERTIES OF VYLONÒ PIPE AND PIPE FITTINGS

 

 

PROPERTY

REQUIREMENT

TEST METHOD

 

 

 

Pipe Material

 

 

 

 

 

Type of Polymer

 

PVC homopolymer

ASTM D-1784

Cell Classifications

12364A

ASTM D-1784

 

Impact Strength

1.5 in.-lbs. (minimum)

ASTM D-256

 

Tensile Strength

6000 psi (cell class minimum)

ASTM D-638

 

Heat Deflection

162°F @ 264 psi (minimum)

ASTM D-648

 

Coefficient of Expansion

2.85 x 10-5 in./in./°F (nominal)

ASTM D-696

 

Thermal Conductivity

 

1.3 BTU/hr.-ft.- °F/in. (nominal)

 

Specific Gravity

1.4 - 1.5

ASTM D-792

 

Modulus of Elasticity

500,000  psi

ASTM D-638

 

 

 

Pipe Property

 

 

 

 

 

Pipe Stiffness

46 psi (minimum)

ASTM D-2412

 

Pipe Flattening

60% deflection (minimum)

w/o cracking

 

ASTM F-1803

Impact Strength

220 ft.-lbs. (30 lb. Tup B 72°F)

ASTM D-2444

 

Extrusion Quality

No flaking, 20 min. in

anhydrous acetone

ASTM D-2152

 

 

 

Pipe Joint

 

 

 

 

 

Rubber Gasket Material

Conforms to

ASTM F-477

 

Joint Tightness

No leakage @ 10.8 psi (22 in.

of Hg Vacuum)

ASTM D-3212